NEW PLANTS · COMPLETE SYSTEMS
Full-plant tenders for new STPs / ETPs
Define process requirements and the technical information that civil, electrical, controls and other packages must address, so offers are priced on a common basis.
RFP and technical schedules · Bid evaluation · Clarifications · Award and contract requirements
A sourcing assignment can begin with an RFP to prepare, a tender package to review, bids that are difficult to compare, or award documents that still need technical closure.
We review the available project basis, identify information that must be resolved, and define the scope boundaries, supplier responsibilities, bidder return requirements and evaluation criteria needed for a controlled tender.
Where bids are already in hand, we normalise the offers, manage technical clarifications and record deviations against the same basis. Agreed requirements are then reflected in the award recommendation, contract technical schedules and delivery requirements.
We develop or review the technical sourcing package so bidders price the same duty, scope boundaries, responsibilities and information requirements.
Supplier offers become difficult to compare when scope, exclusions, operating conditions and required deliverables are not stated consistently. Gaps then reappear during award and delivery.
Bidders respond to a common basis. Clarifications and deviations are recorded before award, and agreed requirements are available for the contract schedules and delivery team.
We define the process-side sourcing requirements and provide the technical inputs needed by the client’s procurement, commercial and legal teams for the issued and awarded documents.
The technical basis must remain consistent even when the contracting route, supplier structure or extent of permitted alternatives changes. Select a route to see the requirements we define.
Scope boundaries, technical requirements and bidder return schedules must be clear before issue. We define the common basis bidders must follow and the information they must provide for evaluation.
SOURCING SUPPORT · PROJECT-LED ASSIGNMENTS
Sourcing support does not require every earlier design activity to be complete. We review the information already available and identify the gaps that affect scope, performance requirements, bidder comparison or award.
We define the RFP so it does more than list equipment: it states how the system must perform across normal, peak and upset conditions, what suppliers must provide, and how deviations will be handled.
The sourcing basis defines:
This gives the client, project team and approval stakeholders a consistent record of what was requested, how bids were compared and what was agreed at award.
Prepare or review the RFP / ToR technical schedules, scope boundaries, supplier responsibilities and bidder return requirements so the market receives one connected basis for issue and comparison.
Define the evaluation matrix, scoring rules, common cost assumptions and treatment of exclusions before issue or before bids are compared.
Manage bidder questions, clarification rounds and deviation schedules so technical changes, cost implications and open conditions remain visible and are reflected in the comparison record.
Support technical negotiations and reflect agreed scope, guarantees, submittals, performance tests and handover requirements in the award recommendation and contract technical schedules.
This support can begin before issue, during tender, after bids are received or before award. It is used when the project team needs a common technical basis to prepare the tender package, compare different offers or close open requirements.
The purpose is to define what suppliers are pricing, how compliance and cost will be compared, which deviations remain open, and what must be reflected in the awarded documents. Commercial and legal teams can then work from the same technical record.
We review the available project information and develop the technical basis suppliers need to price the work. This includes the required duty, scope boundaries, responsibilities, operating conditions, bidder returns and evaluation criteria.
The package can be prepared from the beginning or used to correct and complete an existing RFP. It remains specific on required outcomes and information while allowing defined alternatives to be proposed and evaluated.
Define the procurement scope and supplier responsibilities.
Define the procurement scope and supplier responsibilities.
Allow defined alternatives without changing the required duty.
Set a consistent basis for compliance and comparison.
Compare capital cost with the operating costs and risks attached to each offer.
Assemble the technical schedules and bidder return requirements for issue.
The same sourcing principles apply across different project types, but the technical schedules and bidder returns must reflect the actual procurement arrangement and site conditions.
NEW PLANTS · COMPLETE SYSTEMS
Define process requirements and the technical information that civil, electrical, controls and other packages must address, so offers are priced on a common basis.
EXISTING PLANTS · UPGRADES
State the operating-continuity requirements, connection constraints and temporary process provisions bidders must address while maintaining the required plant duty.
MULTI-SITE · REPEAT PROCUREMENT
Standardise common performance, information and evaluation requirements while retaining site-specific conditions, options and exclusions.
Alternative proposals can be considered provided the required duty, performance obligations and operating constraints remain unchanged. Each alternative should be presented on a common basis so its technical, cost, operating and delivery implications can be compared clearly.
We evaluate each offer against the issued technical requirements, bidder return schedules and agreed evaluation criteria. Scope, exclusions, performance guarantees, cost inputs and supplier assumptions are normalised into a common comparison.
Clarifications and deviations are recorded against the same references, with their technical, cost, operating and delivery implications identified. This provides the client’s procurement, commercial and legal teams with a clear technical basis for negotiation and award.
Check compliance with the required duty, process basis and operating conditions.
Check compliance with the required duty, process basis and operating conditions.
Make scope and cost inputs comparable.
Maintain one referenced clarification record for each bidder.
Present the offers on one transparent comparison basis.
Support negotiations on technical scope, performance and risk.
Close the technical record for award and contract preparation.
Outputs are selected to match the assignment: RFP development, bid evaluation, award support or a combined route. They provide a consistent technical record for issue, comparison, approval and contract preparation.
Templates and schedules can be retained for repeat procurement, with project-specific requirements, assumptions and deviations updated for each tender.
ENGAGEMENT
Sourcing support can begin with incomplete project information, an existing RFP, bids already received or an award that still needs technical closure. We review only what is needed to establish a reliable sourcing basis.
Select the current project condition
Tip
The assignment may cover one part or combine RFP development, bid evaluation, and award support. The scope is based on the information and decisions already available.
Selected project condition
Prepare or review the RFP / ToR, establish a common evaluation basis, compare bids, manage clarifications and close the contract technical schedules.
Relevant sourcing outputs
The review is scaled to the assignment. Some projects need only an RFP or bid comparison; others require missing technical information to be confirmed before procurement can proceed.
Sourcing input
Existing data, design documents, supplier proposals and operating information relevant to the tender.
Sourcing input
Capacity, quality, recovery, reliability and monitoring requirements suppliers must price and guarantee.
Sourcing input
Available process configuration, equipment duties and alternatives that must be resolved or controlled for tender.
Sourcing input
Requirements supplier packages must address for connection, monitoring, operation and performance testing.
Sourcing input
The direct sourcing work required to issue, compare, clarify and close the technical award basis.
Sourcing input
Agreed scope, submittals, guarantees, performance tests and handover records required after award.
Tip: swipe or scroll to browse. Select the project condition that best describes what is available. The sourcing assignment can be scoped from this page without opening the individual service pages.
A sourcing assignment can begin from the project position you have now. Choose the support needed now: RFP development, bid comparison, or award and contract technical schedules. Any information gaps affecting the assignment are identified during scoping.
Pack 1
Prepare or complete the package required to issue the tender on a common technical basis.
Pack 2
Normalise bids, manage structured clarifications and produce a clear comparison and recommendation record.
Pack 3
Close the technical basis for award and reflect agreed requirements in the contract schedules and handover to the delivery team.